Copy a legacy project into the new Schedules

Create a separate project in the new Schedules, check what transferred, then assign categories and locations to the copied products.

Written by Gail Esterhuyse

❓Is this project a good fit to migrate?

We recommend migrating a project only if you haven't shared it with your client yet. We recommend you keep a project as it is if you've shared it with your client, taken their approvals, shared it to the Client Dashboard, or published web links or QR codes for it.

Don't migrate a project that has purchase orders, invoices or approvals in progress. Finish it in your current project.

Use Try the new experience to copy an existing project into the new Schedules model.

This creates a new, separate project. Your original project isn't changed, and it keeps working exactly as it does today, including its purchase orders and invoices.

You can start from the project menu or the migration callout on the project overview.


1. Copy the project

Migrate one project at a time.

  1. Open your legacy project and go to Project Overview.

  2. Select Try it now in the bar at the top.

  3. Or open the … menu at the top right.Select Try the new experience.

  4. Check the preview counts for products, images, files and new labels.

  5. Select Create project.

Programa names the new project [Project name] - Migrated. You can rename it later.

You can continue to work while Programa copies the project. Most copies take a minute or two. A project with many images can take longer.

When the copy is ready, Programa shows a pop-up in the app and emails you a migration report. Check the product and label counts in the report. Use the link to open the new project.

If you run Try the new experience again, Programa creates another new project. It doesn't update your earlier copy.

If a product can't be copied, the rest of the project still copies. The message tells you how many products were left out. Contact support through live chat if you need help with them.


2. Check what transferred

Use this table to check what the new project includes and what you need to add.

Information

What happens when you Migrate

Products

Copied into the new project with their images, attachments, current statuses and order. Archived products are copied and stay archived.

Project files and embeds

Copied into the new project.

Presentations and Pinboards

Copied into the new project.

Tasks, timelines and phases

Copied into the new project.

Clients

Added to the new project with the same access. They aren't emailed, so you can share the new project when you're ready.

Categories

Every product gets auto assigned a main category. Programa predicts it from the product's details.

Section headers

Depends on how your schedule was set up. See How your schedules are organized below.

Products in more than one room

The product is added to each room with a quantity of 0. The original total quantity is saved in the product's notes. Use the Review products link in your migration report to fill in the quantity for each room.

Shipping sections

Shipping fees in their own schedule section are copied as separate products. To link a fee to its product, add the amount to that product's Estimated shipping, then delete the separate entry. Or keep the separate entry and change its category to Fee. It then shows fee fields, but isn't linked to a product.

Legacy schedules

Each schedule becomes a saved view with the same name, pinned to the top of the project. All products are also in All Products.

Product details field

The new Schedules doesn't have this field. Its content is added to the product's Notes under a Product Details: heading. Find Notes in the product's details tray, on the Summary tab.

Flags

Flags become a revision named Internal Flag. The flag text is added to the product notes. Your clients can see revisions, so check these before you share the project.

Tax and markup settings

Stay the same.

Purchase orders and invoices

Not copied. They're linked to the original project and to your accounting software (Xero or QuickBooks), which keeps each invoice number tied to that project. They stay in the original project, which you can keep using for them.

Tracked time

Not copied. It stays in the original project.

Approval history

Not copied. Current product statuses are copied, but the record of who approved what, and when, stays in the original project.

Sharing links and QR codes

Not copied. Existing links keep opening the original project. The new project gets new links.

How your schedules are organized

Programa looks at the section headers in each schedule and sets up the new project to match.

If your schedule's headers are…

In the new project…

All rooms or areas, such as Kitchen or Bathroom

Each product is assigned the location of the section it was in. The new project is grouped by location, to match your old setup.

All categories, such as Lighting or Joinery

Each product is assigned a category automatically. The new project is grouped by main category.

A mix of headers, or anything else

Each product is assigned a label named after the section it was in. The new project is grouped by label.

All blank

Products get one label named after the schedule, with no grouping.


3. Complete the new project

Check product categories. Every product has a predicted main category. Change any that are wrong. The category controls which technical fields the product shows. To change several products at once, use a bulk action.

Add locations and allocate quantities. If your headers became locations, check them. If they became labels, add the rooms or areas that use each product, then divide the quantity between them. All locations share the same product record.

Fill in quantities for products in more than one room. These start at 0 in each room. Use the Review products link in your migration report to find them. The original total is in each product's notes.

Review Internal Flag revisions. Your clients can see revisions. Resolve or update any flags you don't want clients to see before you share the project.

Move shipping fees. If you had a shipping section, add each fee to its product's estimated shipping and delete the separate entry, or change its category to Fee.

If a saved view uses a label, add that label to new products. A product without the label won't appear in that view. It still shows in All Products.

Labels and locations are different. In a mixed schedule, a header such as "Kitchen" becomes a label, not a location. Adding a product to the Kitchen location won't put it under the "Kitchen" label.

Share the new project with your clients. Your clients have access to the new project but aren't notified. Send them the new project's links when you're ready. Old links still open the original project.

Choose which project your team will use. Once you've moved your work to the new project, we recommend archiving the original to avoid confusion, unless you still need it for purchase orders or invoices.


If you can't copy the project

A failed copy doesn't change your original project. Check the message you see:

If you see…

What to do

"Unarchive this project…"

Unarchive the project, then try again.

"A meeting… is still recording"

Wait for the recording to finish, then try again.

"A meeting you can't open"

Ask the meeting's host to share it with you, then try again.

"The setup stopped" or "We couldn't set up the new project"

Try again. If it fails a second time, contact support through live chat.

"Content the new project can't hold yet"

Contact support through live chat and include a link to the project.

"Your clients wouldn't have exactly the same access"

Contact support through live chat.

Don't see Try the new experience?

The new Schedules is rolling out to studios in stages. If you don't see Try the new experience, it isn't available for your studio yet.

Did this answer your question?