How to set up Procurement in your Schedule

Set a procurement status, add order, delivery and payment dates, record tracking details and attachments, and update dates on many products at once.

Written by Gail Esterhuyse

Procurement is on for every product

You don't need to switch anything on. A product appears in Procurement Hub as soon as it has a Procurement status or a procurement or payment date.


Setting a procurement status

Select a product's status and choose a status from the Procurement group: Quoting, Quote accepted, Quote rejected, Ordered, In production, In transit, Delivered or Installed. Choose Not ordered to clear it.


Adding dates to a product

  1. Open the product's details and select the Procurement tab.

  2. Set any of the eight dates:

  • Procurement dates: Ordered, Shipped, Delivered, Installed

  • Payment dates: Client deposit, Supplier deposit, Client balance, Supplier balance

To remove a date: Hover over the date and select the X. This clears it from your Schedule and removes it from Procurement Hub.


Adding order and shipment details

In the same Procurement tab, you can add:

  • Order reference: a purchase order number, supplier invoice number, quote reference or your own reference

  • Tracking number: the carrier's tracking code

  • Tracking URL: a link to the carrier's tracking page

  • Shipment notes: delivery instructions, special handling or other details

Tip: Add an order reference so you can filter by it in Procurement Hub.

Attachments: Drag and drop files into the upload box, or select it to browse your files.

Note: Procurement attachments aren't published to your shared Schedule. To share documents with clients, upload them to the product's attachments instead.


Setting a date on many products at once

Select products in your Schedule, open the bulk Actions menu, then choose Change procurement date… or Change payment date…. Pick the date field and the date, then select Update products.


Ticking off a completed date

Once a date is done (a deposit paid, a delivery received), tick the checkbox beside it in the Procurement tab. When all of a product's dates are complete, the product leaves Procurement Hub.

You can also mark due dates complete on many products at once from Procurement Hub. Learn how to use bulk actions in Procurement Hub.

Note: The Procurement tab also shows the invoices the product is attached to and its Purchase orders, which you can download as PDFs.


Need more help with procurement setup? Contact our support team via live chat for personalized assistance.